Project Logistics & Route Planning
Project-cargo route, port, customs, lifting, storage and site-delivery planning.
Tender Practical Guides
A control model for shipping documents, customs readiness, storage, receiving inspections, preservation and final delivery to the installation work front.

Shipment readiness should include documentation readiness. Commercial invoice, packing list, certificates of origin, transport documents, customs classification, permits and project-specific exemptions or approvals should be checked before dispatch. Missing or inconsistent documents can convert transport time into uncontrolled customs dwell time.
The customs plan should distinguish what the contractor controls from what depends on the Employer, importer of record, customs broker or authority. Responsibility for exemptions, temporary imports, re-export, taxes, inspections and guarantee deposits should be explicit because ambiguity can trap equipment at the border while each party waits for another to act.
Site receiving is a formal control point. Quantity, visible damage, packaging condition, preservation status, serial numbers and required documentation should be checked before responsibility transfers into storage or installation. Claims against carriers or suppliers become harder when damage is discovered days later without receiving evidence.
Storage and preservation requirements should follow equipment needs, not generic warehouse practice. Moisture, temperature, rotation, battery maintenance, desiccant replacement, periodic inspection and covered storage may be required. The logistics plan should preserve warranty and commissioning readiness while equipment waits for installation.
The last mile ends at the work front, not at the project gate. Delivery should be sequenced with lifting capacity, access, foundations, embedded items, weather and installation crews. A logistics KPI based only on 'arrived at site' can hide weeks of internal delay before equipment becomes installable.
Related services
These Gokbilge capabilities connect the article's subject to practical tender, commercial, engineering and project-delivery controls.
Project-cargo route, port, customs, lifting, storage and site-delivery planning.
Sourcing, vendor data, expediting and purchase-order coordination feeding logistics readiness.
Project quality planning, ITP and inspection control, material traceability, vendor and site quality surveillance, NCR management and turnover-document readiness.
Owner-side and programme-level construction management, contractor coordination, supervision, progress verification and site governance for multidisciplinary works.