Employer data and reliance
When provided information can or cannot support price assumptions.
Tender Practical Guides
How site investigations, geotechnical baselines, rock classifications, groundwater data, reliance clauses and physical-condition relief mechanisms should be tested before pricing excavation, foundations, tunnels, dams and major earthworks.

Ground risk is rarely just a geotechnical issue. It is a contract-definition issue, a quantity issue and a schedule issue at the same time. A bidder should distinguish information provided 'for information', information that may be relied upon, contractual baselines and actual risk allocation under the Conditions of Contract. A thick geotechnical report does not protect the contractor if the contract says the contractor is deemed to have independently verified all subsurface conditions.
The pricing questions are practical: what proportion of excavation is soil, weathered rock or hard rock; what ripping or blasting restrictions apply; what groundwater pumping is foreseeable; are disposal areas available; is excavated material reusable; are foundation levels fixed; and what happens if weak strata extend below the assumed depth? Each assumption should be linked to a measurable baseline or a clarification. Otherwise the contingency can become arbitrary.
The no-bid threshold appears when the risk is both high-impact and unbounded. Examples include deep foundations with little subsurface data, tunnel alignments with no meaningful baseline, dredging where contamination and material classification are undefined, or a dam foundation where the contractor assumes all geological treatment without a relief mechanism. These risks can exceed the entire expected project margin.
The bid team should therefore create a ground-risk register separating quantity variance, productivity variance, equipment-method change, disposal, groundwater, support/temporary works and programme effects. If the contract provides relief for unforeseeable physical conditions, the team must also understand notice, records and comparison-baseline requirements before relying on that relief commercially.
This article is engineering and tender-risk guidance. The signed bidding documents, conditions of contract, technical specifications, drawings, bill of quantities, method of measurement and applicable law govern each project. Contractual and legal interpretations should be confirmed by qualified advisers where material.
Related articles
These articles cover adjacent decisions and controls that are useful when applying the guidance in a live tender or project.
When provided information can or cannot support price assumptions.
How geological uncertainty becomes quantity and payment exposure.
Related services
Gokbilge helps tender and project teams convert bidding rules into compliance matrices, qualification evidence, technical-commercial alignment, controlled approvals and post-award execution systems.
Tender specification review, technical clarifications, quantity and interface analysis, and risk allocation before bid submission.
Bid/no-bid gates, risk registers, programme assumptions, change control and post-award evidence management.
Turning tender assumptions into executable design, procurement, construction, testing and commissioning controls.
Sources
Official ADB guidance for admeasurement works procurement using FIDIC Red Book 2017, including Works Requirements and contract structure.