Commissioning starts before construction finishes
Commissioning is often described as the final stage of a project, but readiness has to be managed much earlier. System boundaries, test philosophy, energization sequence, vendor involvement, temporary utilities, operating procedures and acceptance criteria influence engineering and construction decisions long before the first functional test is performed.
When commissioning is left until the end, the commissioning team inherits incomplete documentation, unresolved punch items, missing vendor support and systems that were constructed by area rather than prepared by functional boundary. The result is a test programme that spends its time discovering construction incompleteness instead of verifying performance.